|

|
 |
|
|
| |
|
| |
|
|
Central
Square Manhole Separation Project
City
of Cambridge Sewer Maintenance and
Stormwater Management Project
- Click HERE to view the contract area in GIS and HERE for GIS viewer tips.
|
| |
|
|
|
Project
overview |
|
| |
The
City of Cambridge has awarded
a contract to P. Gioioso &
Sons to separate 22 common manholes
and clean 2 other manholes in
the Central Square area. The
locations of these manholes
include Mass Ave (between Clinton
St and Lafayette Square), Clinton
St, Inman St, Essex St, Norfolk
St, Bishop Allen Dr, and Douglass
St.
|
|
| |
|
| |
|
|
|
Why
is this project necessary? |
|
| |
This
work is required by the Massachusetts
Department of Environmental
Protection, in order to improve
water quality in the Charles
River. This project will reduce
incidents of sewage backups
into certain properties and
will improve the quality of
stormwater discharges to the
Charles River. It is part of
a citywide effort to improve
the Cambridge’s drainage
system and water quality in
our local rivers.
|
| |
|
|
|
What
will be done to fix the problem? |
|
| |
The
contractor will set up a protected
work zone of approximately 20ft
by 50ft when separating each
common manhole. He will then
use large construction vehicles
to dig down approximately 12
ft, to remove the old common
manholes and install new separate
stormwater and sewer manholes.
He will post “No Parking”
signs and may have to take space
in the roadway to operate. Pedestrian
access and access into properties
will be maintained, but may
be restricted in certain ways.
Manhole locations will be temporarily
patched with asphalt after being
separated. As part o a follow
up contract next spring, sidewalks
and streets will be permanently
restored. |
| |
|
|
|
Who
is responsible for the project? |
|
| |
P.
Gioioso & Sons. of Hyde Park
is the contractor for this project,
which was bid as Common Manhole
Contract 4. This contract is managed
by Department of Public Works
staff as part of collection system
maintenance, with engineering
services provided by consultants
MWH and SEA. |
| |
|
|
|
What
is the project schedule? |
|
| |
Construction
on this contract is expected to
start in September 2008, and will
be ongoing for approximately one
year. Each individual manhole
will take approximately 3-4 weeks
to separate. |
| |
|
|
|
How
can I get more information or
assistance related to this project? |
|
| |
For assistance during this project, including any accommodations related to a disability or special need, please contact Kelly Dunn, Community Relations Manager, at 617-349-4870 or kdunn@cambridgema.gov.
|
| |
|
| |
Recent
Construction Updates
- 07/29/2009:
- Drainage work will continue across from Norfolk Street for approximately two weeks. Click here to view the detailed notice. The next scheduled work location is behind city hall on Dottie Doyle Way.
- 07/16/2009:
- Work crews will begin work at 526 Mass Ave, across from Norfolk Street. Click here to view the detailed notice.
- 05/29/2009:
- Due to MIT graduation
on June 5th, the contractor
will only be working 4
days next week, Mon-Thurs;
however, work hours will
be slightly longer (7:00
am - 5:30 pm) in order
to avoid falling behind
on their overall schedule.
- 05/22/2009:
- 05/01/2009:
- Crews on Mass Ave in
front of Central Kitchen
and at Brookline expect
to move to new sites on
or shortly after May 6:
- 04/01/2009:
- Crews working on Mass
Ave at Pearl St and Clinton
St expect to move to new
sites on or shortly after
April 5:
- 03/12/2009:
- On Monday, March 16,
new phase of work to start
on
- After 1 week snow-related
delay, on Monday, March
9, crews started at
- 02/12/2009:
- On Tuesday, Feb 17,
crews from the Mass Ave
at Pleasant St site move
to:
- 01/29/2009:
- On Monday, Feb 2, crews
move from the 450 Mass
Ave site to:
- 01/15/2009:
- Crews start at 2 new
locations on Monday, Jan
19:
- 12/4/2008:
- 11/13/2008:
- Thur 11/13 - Fri
11/14- Test pits
on Bishop Allen Drive
at Essex and Douglass
streets. Each test pit
requires a several on-street
parking spaces be occupied
for a period of 1-2 hours,
during which time a small
excavation is made to
field verify utility locations.
- Fri 11/14- manhole work
starts on Norfolk
St.
- 10/17/2008:
- Mon 10/20 - Tues
10/21 test
pits throughout the project
area- Norfolk St, Austin
Park, and Bishop Allen
at Austin Park, Vail Court,
Essex St, and Douglass
St. Each test pit requires
a several on-street parking
spaces be occupied for
a period of 1-2 hours,
during which time a small
excavation is made to
field verify utility locations.
- Tues 10/21 or Wed
10/22 manhole works
starts at 55
Essex St.
- On or shortly after
Wed 10/22 manhole
work starts in the Austin
Park/ Vail Court/ Bishop
Allen area.
|
|
|
|
|
|
|