Porter
Square Drainage and Surface Improvement
Project
City
of Cambridge Stormwater Management
and Surface Enhancement Project
|
| |
|
|
|
Project
Overview |
|
| |
In
November 2004, the City’s
contractor, J. F. White Contracting
Company, began construction on
the Porter Square Drainage and
Surface Improvements Project.
The project —which includes
a portion of Mass Ave (from Upland
Rd to Beech St), White St, and
the Cambridge portion of Somerville
Ave— will enhance streets
and sidewalks and reduce flooding.
Construction will take approximately
16 months to complete. |
View
Map of Project Area |
| |
| |
|
|
|
Why
is this Project Necessary? |
|
| |
From
1997 to 2004, a Citizen Advisory
Committee worked with the City’s
Community Development Department
to analyze many options for
improving the safety and function
of Porter Square for all users.
The Committee agreed upon the
following goals:
- Reduce vehicular domination
of Porter Square
- Improve conditions for
pedestrians, bicyclists, and
transit users, particularly
for pedestrians crossing Somerville
Ave at the T stop
- Reduce cut-through and
shopping center related vehicular
traffic on neighboring residential
streets
- Improve the streetscape
and create a sense of place
in Porter Square
- Improve traffic safety
Construction on these surface
improvements provides an opportunity
to make much needed drainage
improvements to minimize flooding
in this area. |
| |
|
|
|
What
is Being Done to Fix the Problem? |
|
| |
The
following surface improvements
were designed based on the Citizen
Advisory Committee's goals:
- Seven additional crosswalks
and improved crosswalk markings
to give pedestrians more direct
access and more options for
crossing
- Reduced delay at signalized
crosswalks and additional
crossing time
- A left-turn out of the
shopping center onto southbound
Mass. Ave
- An exclusive right turn
lane from northbound Mass
Ave to Somerville Ave
- An enlarged plaza to enhance
Porter Square and create a
new sense of place
- Bicycle lanes added through
the project area and partial
removal of median
Construction on these surface
improvements provides an opportunity
to make the following much needed
drainage improvements to minimize
flooding in this area:
- Installation of 29 catch
basins in Mass Ave, Somerville
Ave, and White St
- Installation of approximately
550 feet of new storm drain,
with associated manholes,
in White St
- Lining of approximately
1,200 feet of combined sewer
in Mass Ave and Somerville
Ave
- Water main replacement
and removal of lead services
in White St
|
| |
|
|
|
Who
is Responsible for the Project? |
|
| |
The
City's contractor for this project
is J. F. White Contracting Company
of Framingham. The surface improvements
for this project were designed
by the Cambridge Community Development
Department, working with the Porter
Square Citizen Advisory Committee,
Earth Tech Consultants, Halvorson
Design Partnership, and the Cambridge
Arts Council. The drainage improvements
were designed by the Cambridge
Department of Public Works, working
with Montgomery Watson Harza and
SEA Consultants. |
| |
|
|
|
What
is the Project Schedule? |
|
| |
Construction
on this project began in November
2004, and will take approximately
16 months to complete. Final
roadway paving and completion
of the plaza are scheduled for
spring 2006.
General work hours for this
construction will be Monday
through Friday, 7 AM to 5 PM.
Evening and weekend construction
will be minimized to the greatest
extent possible, and will be
limited to certain types of
utility work or emergency situations.
|
| |
|
|
|
Who
Will Address My Concerns? |
|
| |
The
City of Cambridge recognizes
that during construction in
Porter Square, it is important
to consider the needs of businesses,
residents, pedestrians, bicyclists,
and drivers. We are committed
to managing this construction
in the most effective manner
possible. Bruno Cardarelli,
Senior Resident Engineer for
SEA Consultants, will be on
site daily to ensure that the
best construction practices
are observed. If you need assistance
during construction, please
call Bruno at (617) 234-0030.
If you have any questions or
concerns during this construction,
please contact Rebecca Fuentes,
Community Relations Manager
for the Department of Public
Works at (617) 349-6948/ rfuentes@cambridgema.gov;
please also contact Rebecca
if you have a special need
or disability that
requires an accommodation or
continuation of special services
during construction. If you
are directed to Rebecca’s
voicemail, you will have the
option of leaving a message,
or connecting to the receptionist,
who can page a member of the
project team in the field in
the case of an emergency.
If
an emergency arises after hours
or on weekends, please call
the 24-Hour line at (617) 349-4860.
Thank you in advance for your
patience during construction.
We hope you enjoy these improvements
to Porter Square once they are
completed.
|
| |
|
|
|
|
|
|
|