|

|
 |
|
|
| |
|
| |
|
|
Rindge
Ave Improvements (Middlesex
St to Alewife Brook Pkwy)
City
of Cambridge Surface Enhancement Project
|
|
|
Project
updates |
|
| |
05/07/2008-
The City's contractor, Aggregate
Industries, has completed all
sidewalk excavation, curb installation,
and rough grading on Rindge
Avenue. They are currently working
with various utility companies
to adjust the height of metal
structures in the sidewalk,
with the expectation that they
will be in a position to fine
grade, place forms, and place
concrete once the structures
have been adjusted. Concrete
work could begin as early as
next week, and will include
a number of driveway aprons;
impacted properties will be
contacted directed to coordinate
when driveways will be out of
service to allow the placement
and curing of concrete.
The City has been working to
plant trees on both the public
sidewalk and the private back
of sidewalk (described in the
4/3 update posted below). Click
here to view a map
of locations that have been
identified to date for tree
planting [note that this map
only shows Cambridge street
trees, not park trees or trees
on property owned by others].
04/03/2008-Construction
to Start, Back-of-Sidewalk Tree
Planting
03/17/2008- TV/
Cleaning Notice
03/14/2008-Project
Overview
|
|
| |
|
|
|
|
Project
Overview |
|
| |
The
City’s contractor, Aggregate
Industries, will reconstruct
all pedestrian ramps, repair
selected sections of sidewalk,
and pave the roadway on Rindge
Ave (from Alewife Brook Parkway
to Middlesex St).
This project will create safe,
accessible ramps and crossings
along this section of Rindge
Ave, which is heavily used by
pedestrians because of amenities
such as the school, library,
pool, parks, and MBTA bus stops/
station. Street paving is particularly
needed on this section of Rindge
Ave due to recent utility improvements
Key pedestrian improvements
include:
- Curb extensions at the
entrance to Russell Field
and at Jefferson Park
- Create better sightlines
and reducing crossing
distances
- Provide an opportunity
for additional green space
at Russell Field
- Do not affect on-street
parking, as these are
existing no parking zones
- Curb extension at Clifton
St
- Creates additional
sidewalk width needed
to preserve the large,
mature tree at 293 Rindge
Ave while creating an
accessible pedestrian
route
- Removes approximately
2 on-street parking spaces
- Widened sidewalk adjacent
to Cemetery (between Clay
and Sherman streets)
- 5 additional feet of
sidewalk provides access
for pedestrians and maintains
the 4 large trees
- Removes parking on the
north side of Rindge Ave
between Montgomery and
Clay streets
See
detailed construction plans>>
Through the Rindge Ave improvements,
gray rubber sidewalk panels
will be installed adjacent to
the four mature trees next to
the Cemetery in order to reduce
the amount of lifting by tree
roots. These panels—which
have been used on similar locations
in other cities— will
be monitored to ensure they
provide an acceptable walking
surface in all types of weather,
are durable enough to withstand
weather conditions, and conform
to growing roots in a desirable
manner.
Learn
more about rubber sidewalks>>
|
View
Image of Large Tree, 293 Rindge
Ave
View
Image of Mature Trees next to
Cemetery
|
|
| |
|
|
|
Who
is Responsible for the Project? |
|
| |
The
City's contractor for this project
is Aggregate Industries. DPW
Construction Project Manager,
Artie O'Brien, will be on site
daily to ensure best construction
management practices are observed.
“No Parking Signs”
will be posted 24 hours in advance
of all work. Signage and police
details will be in place to
assist during traffic disruptions.
The contractor will work with
impacted property owners to
coordinate and limit any disruptions
to the greatest extent possible.
|
| |
|
|
|
What
is the Project Schedule? |
|
| |
Preparatory
cleaning of sewer lines (through
a separate maintenance contract)
started in early March. Installation
of drainage structures will
begin the first week in April
2008, with significant sidewalk
construction expected to start
the third week of April 2008.
Overall, this project is expected
to be completed by early June
2008.
General work hours for this
construction will be Monday-Friday,
7 a.m. to 5 p.m. Evening and
weekend construction will be
minimized to the greatest extent
possible.
|
| |
|
|
|
Who
will Address My Concerns? |
|
| |
For
information or assistance, or
for accommodations of special
needs and/or disabilities,
contact Rebecca Fuentes at (617)
349-6948/ rfuentes@cambridgema.gov.
We also send out project updates
by e-mail; please e-mail
rfuentes@cambridgema.gov
to sign up for this distribution
list.
If an emergency arises after
hours or on weekends, please
call the 24-Hour line at (617)
349-4860.
Thank you in advance for your
patience during construction.
We hope you enjoy these improvements
once they are completed.
|
| |
|
|
|
|
|
|
|