City Manager
City Council
Departments
Pay Bills
Jobs
Calendar
Home
The Cambridge Department of Public Works
• Information & Hotlines
• Schedules
• News & Updates
• Maps
• Permit Applications
• FAQs
• DPW Home

Construction Information

cambridgeMa.gov
 
       
 

Walden Street Bridge
Commonwealth of Massachusetts- Bridge Reconstruction Project

 Overview    Project Necessity    Traffic Impacts   Responsibilities   Schedule   Concerns

  Project updates
 

05/01/2008- Massachusetts Highway Department’s (MHD) contractor for the Walden Street Bridge reconstruction project, J. F. White Construction, recently submitted a schedule to MHD projecting a revised project end date of late March 2009. This would extend the bridge closure approximately 6 months past the originally scheduled end date.

The revised protracted schedule is primarily due to bridge pier/abutment redesign and construction issues. The new bridge is to be supported by three abutments: one to the north, one to the south of the bridge and one immediately south of the historic cow path (essentially in the middle of the bridge). In drilling the shafts that provide structural support for the piers/abutments, the alignment of the shafts shifted and thus additional analysis and redesign was required so as to ensure that there was no compromise in the structural support provided by the piers. The reinforcement steel pattern was also revised so as to assure adequate structural support.

Additionally, as a result of excavation activities associated with the construction of the center pier/abutment, and after examining the foundation of the historic cow path adjacent to the center pier/abutment it was determined that the pier/abutment should be relocated away from the arch (approximately 18 inches) so as to ensure the continued stability of the cow path. Furthermore, it has been determined by MHD that further interim measures needed to be taken to stabilize the arch itself during construction, such as internal bracing, grouting the foundation of the cow path, repointing the bricks within the arch and modifying excavation activities so as to balance forces acting on the arch. At this time the contractor estimates that as a result of the delays associated with the redesign and the additional construction activities required, the contract will extend into the spring of 2009.

MHD is presently reviewing the revised schedule proposed by the contractor and is working with them to assess means of expediting some of the work associated with the construction.

Finally it should be noted that the revised structural design will not impact the appearance of the bridge from street level. MHD has again committed to continue to update the City as construction moves forward. To that end, the Department of Public Works will continue to inform residents with updates and will provide information on its web page with project progress.

3/25/2008- Based on conversations with MassHighway, the City has the following update:

  • In mid-February, the contractor re-mobilized on-site, and has been working on the historic cow path and other preparatory activities on the Mass Ave side.
  • The historic cow path was found to be in fairly fragile condition, and was moved up in the construction schedule in order to stabilize the arch structure before additional demolition takes place. The contractor is currently pointing the existing brickwork to strengthen the cow path arch under heated tarps (visible from the pedestrian bridge).
  • Work on the cow path is scheduled for completion in late March. In early April, removal of the remaining existing north wall/ abutments will begin.
  • The design and construction issues related to the new bridge abutments have been substantially resolved, and so abutment work is planned to proceed this spring.

12/20/2007- Construction has been delayed due to the failure to one of the shafts. The bridge design is being modified due the failure. More information will be posted when it becomes available.

For information and assistance related to this project, please contact Sean Magnus, MassHighway’s Resident Engineer, at (617) 491-1215.

Previous Construction Updates:

   
Project Overview  
 

The Walden Street Bridge, which spans the MBTA commuter rail tracks between Richdale Avenue and Mead Street, is in disrepair and in need of replacement.

MassHighway’s design process for a replacement bridge began several years ago and included a public hearing in April 2000. As a result of input from the design process, MassHighway agreed to provide a temporary pedestrian bridge during the time the bridge was closed, modify the pavement markings to maintain the current travel lanes and parking layout, reconstruct curb ramps at intersections, and re-paint crosswalk, and to restore the historic brick cattle pass under the bridge as part of the project. Based upon recent neighborhood input, the State has agreed to certain aesthetic improvements to the bridge design.

View Artist's Rendering of New Bridge
 
   
Why is this Project Necessary?  
  The focus of this project is to provide a safe, structurally secure bridge.
   
What Impact Will This Project Have on Traffic?  
 

In order to replace the bridge, it must be entirely closed to vehicle traffic during construction. A temporary bridge for pedestrians and bicyclists will be constructed to maintain access for those users during construction; drivers will be required to use the detours described in the attached detour map.

Signs will be posted along the detour routes to alert drivers of this change. The City will monitor the detour routes for effectiveness and will make changes as needed.

   
Who is Responsible for the Project?  
  The Walden Street Bridge is owned by the Massachusetts Highway Department (MassHighway), who has hired JF White Construction to reconstruct the bridge.
   
What is the Project Schedule?  
 

Construction started October 10, 2006,and will take approximately 2 years to complete. The bridge will be fenced off and closed to vehicle traffic for the duration of construction.

Most construction will take place during standard work hours, Mon through Fri, 7 am to 4 pm. However, because of the MBTA railroad tracks, certain operations must be scheduled off-hours, at night or on weekends. MassHighway has agreed to notify direct abutters in advance of off-hours construction whenever possible.

 
Who Will Address My Concerns?  
 

MassHighway resident engineer Sean Magnus is overseeing this project. He can be reached at the project field office phone number: (617) 491-1215. Please visit the MassHighway Website for more information: http://www.mhd.state.ma.us/ (click on the ProjectInfo Icon in the bottom left-hand corner).

The City's contact for this project is Bill Deignan, Transportation Planner from the Community Development Department, wdeignan@cambridgema.gov/ (617) 349-4632.

The DPW operates a 24-Hour Phone Line, in the case of an emergency: 617-349-4860. The City will also be sending out periodic construction updates via e-mail; please e-mail rfuentes@cambridgema.gov to be added to the distribution list.

Thank you in advance for your patience during construction.

 
--- top ^

     

 
 © 2003 Department of Public Works, City of Cambridge, Massachusetts
City of Cambridge Home Page