Walden
Street Bridge
Commonwealth
of Massachusetts- Bridge Reconstruction
Project
|
|
|
Project
Update 3/14/07 |
|
| |
The temporary pedestrian bridge
will be lifted off the existing
structure and placed on its
foundations on Friday night
3/16.
This will also coincide with
the final shift of night work
for now. MassHighway has installed
all of the demolition shielding
over the tracks and will attempt
to finish shielding that is
not directly over the tracks
with daytime track diversions.
This represents a significant
milestone in the project. Phase
II gas and electrical relocations
can now begin. NSTAR has projected
eight weeks for this work. Once
these relocations are complete
and the ramps to the bridge
are installed, the bridge will
open for pedestrians. This will
represent the next major milestone
in the project as demolition
of the existing structure can
begin.
If you have any questions,
please contact Bill
Deignan by e-mail
or by phone at (617) 349-4632
|
|
| |
| |
Previous Updates:
February
5, 2007 Construction Update
January
30, 2007 Construction Update
January
19, 2007 Construction Update
December
18, 2006 Construction Update
(pdf)
October
4, 2006
(submitted by Rep
Alice Wolf)
|
| |
|
|
|
|
|
|
|