New Phase of Construction
to Start:
Starting next Monday, June 4,
MassHighway's contractor, JF
White Construction, will begin
drilling for new bridge supports.
This is a daytime operation,
Monday-Friday, 7 am to approximately
4 pm. This work is expected
to take approximately 6 weeks
to complete.
MassHighway Resident
Engineer:
Also please be advised that
MassHighway has a new Resident
Engineer working on this project,
Mr. Nicholas DelVento. Mr. DelVento
can be reached at the Field
Office phone number, (617) 491-1215.
|
|