Walden
Street Bridge
Commonwealth
of Massachusetts- Bridge Reconstruction
Project
|
|
|
Project
Update 08/07/07 |
|
| |
MassHighway's contractor, JF
White Construction, will begin
demolishing the old Walden Street
Bridge on Monday, August 13th.
Because of the railroad operating
below the bridge, the contractor
has closely coordinated with
the Massachusetts Bay Commuter
Rail Company to develop the
following schedule:
- Deck demolition: August
13th - 22nd daytime construction
- Steel superstructure removal:
August 27th - 31st nighttime
construction
For information and assistance
related to this project, please
contact Nicholas DelVento, MassHighway’s
Resident Engineer, at (617)
491-1215.
|
|
| |
| |
Previous
Construction Updates:
- June
4, 2007
- May
2, 2007
- April
30, 2007
-
April 9, 2007
- March
27, 2007 Construction Update
- March
14, 2007 Construction Update
- February
5, 2007 Construction Update
- January
30, 2007 Construction Update
- January
19, 2007 Construction Update
- December
18, 2006 Construction Update
(pdf)
- October
4, 2006
(submitted by Rep
Alice Wolf)
|
| |
|
|
|
|
|
|
|