Main Street Reconstruction Project

Includes Ames St to Wadsworth St

August 2015

During the month of August, crews will be focused on reconstructing the sidewalks on the north side of Main Street. The north side of Main Street (sidewalks) is expected to be completed by the end of this month. Once the north side has been completed, crews will begin to reconstruct the south side of Main Street.

 

April Activity

During the week of April 21, sidewalk and roadway reconstruction will begin.  The road work will take about one month to complete and the sidewalk work will be ongoing through the spring and summer.

We expect construction activities to resume in the fall of 2015.  

February Activity

Crews will mobilize on Main St on Wednesday, February 25 to begin removing the deteriorated pear trees from the project area.  The trees have structural flaws that make them susceptible to storm damage.  Crews will plant a total of 58 new trees , from 5 different species at the end of the construction this fall.  For more information on the Main St tree plan, please visit the Documents tab.

 

March/April Activity

In mid-March, crews are expected to resume utility work on the north side of Main St, between the MBTA station and Ames St.  In April, construction activities will ramp up with crews starting road and sidewalk reconstruction.  We expect the surface work to continue through the summer.

We expect construction conclude this fall 2015. 

 

 

Project Background 

Through the Kendall Square Planning Study (K2C2 ), a plan of improvements for Main Street (Ames to Wadsworth) has been developed. The plan will provide a high quality experience for pedestrians and cyclists with reconstructed sidewalks and roadway, enhance transit accommodations, provide a new connection from Third St to Main St, and include seating, bus shelters and bike parking, including artist designed bike racks. 

Please also check the K2C2 website for more information on this project.

 

For more information on the Main Street project, please contact Dan Vallee, project manager, at 617.349.4813.

 

For more information about the K2C2 study, please contact Iram Farooq at ifarooq@cambridgema.gov /617.349.4606. The Community Development Department TTY line is 617.349.4621.

How can we help you? I'd like...

Mobile Cambridge

Keeping you connected wherever you are. Learn more about Mobile Cambridge

FAQ's

Have a question?
Find the answer in our extensive
Frequently Asked Questions

Dept of Public Works

147 Hampshire St
Cambridge MA 02139

Phone:617.349.4800
TDD:617.499.9924

Hours of Service

Monday: 8:30am-8:00pm
Tuesday-Thursday: 8:30am-5:00pm
Friday: 8:30am-12 noon
24 Hour emergency 617.349.4860

RECYCLING CENTER HOURS

Tuesday & Thursday: 4:00pm-7:30pm
Saturday: 9:00am-4:00pm

Owen O'Riordan
Commissioner