Cambridge Common and Flagstaff Park

The Cambridge Common and Flagstaff Park project aims to rehabilitate all aspects of the Common as well as improve conditions for all users of these parks and those travelling along this section of Mass. Avenue, from Garden Street to Cambridge Street. It also seeks to unify the historic landscape of the Common by simplifying the vocabulary of the design. The planning of the project has been underway for many years, along with securing funding for the nearly $4m project. The project will replace all pathway surfaces on the Common to meet access codes with bituminous paving with a brick edge, replace and upgrade all benches and trash cans, plant over 100 trees and remove older under-story plantings, improve drainage and turf surfaces, and rehabilitate the lighting system to extend its life and add lighting to pathways where it is missing.

Across the street, along the Mass. Avenue side of Flagstaff Park, the curbs will be moved out and a two-way multi-use path constructed with crossings at each end to create better bicycle and pedestrians connections between Harvard Square and Mass. Avenue northbound.

July 28, 2014

Crews are currently performing work inside of the Cambridge Common.

------------------------------------------------------------------

July 14, 2014

This week, crews will be working on Massachusetts Avenue at Flagg Staff park, removing the media. Early next week, crews are expected to make their way into the Cambridge Common to begin construction.

------------------------------------------------------------------

June 30, 2014

There will not be any significant work this week.

----------------------------------------------------------------------------------

June 23, 2014

This week crews continue to place temporary fencing around the Cambridge Common. Crews will be performing more tree protection in the area as well as restriping the lanes near Flag Staff Park at Massachusetts Avenue. Work at Flag Staff Park begins shortly and will be completed in 6-8 weeks.

----------------------------------------------------------------------

June 16, 2014

This week, crews are beginning to perform work associated with the new multi-use path through Flagstaff Park. The work this week is located at the Massachusetts Avenue/Garden Street/Peabody Street intersection. Police officers will be on site to assist with traffic management.

-----------------------------------------------------------------------

June 11, 2014

As part of the rehabilitation of the Cambridge Common and Flagstaff Park, MassDOT’s contractor, Newport Construction will mobilize on Massachusetts Ave near the intersection of Garden St on Thursday, June 12. Crews will reconstruct the roadway on Massachusetts Ave and also construct a two-way, multi-use path to improve bicycle and pedestrian connections between Harvard Square and Massachusetts Avenue northbound. We expect the road work on Massachusetts Ave to be ongoing for the next 2-3 months. Improvements within the Cambridge Common will begin in mid-July and will continue into next year.

-----------------------------------------------------------------------

June 9, 2014

Crews will mobilize on Mass Ave at Garden St on Thursday, June 12 to begin road work.  The road work will be ongoing for 2-3 months.

-----------------------------------------------------------------------

June 2, 2014

This week, the states contractor, Newport Construction, will be placing a variable message board on Massachusetts Avenue to alert pedestrians, cyclists and motorists of the upcoming work. Next week, crews will begin to work on Massachusetts Avenue. Motorists should expect delays.

----------------------------------------------------------------------------------------

May 28, 2014

The states contractor, Newport Construction, is in the midst of coordinating meetings with agencies that will be effected by construction on the Cambridge Common.

-----------------------------------------------------------------------

May 19, 2014

Newport Construction, MassDOT's contractor, will continue with light activity, such as surveying, throughout the week.

-----------------------------------------------------------------------------------------

May 12, 2014

Newport Construction, MassDOT's contractor, will begin light activity, such as surveying, throughout the week.

-----------------------------------------------------------------------------------------

April 28, 2014

Newport Construction, MassDOT's contractor, will begin light activity, such as surveying, throughout the week.

----------------------------------------------------------------------------------------

April 23, 2014

Newport Construction is currently awaiting a notice to proceed with the work from the Massachusetts Department of Transportation.

----------------------------------------------------------------------

March 26, 2014

The Massachusetts Department of Transportation has awarded the Cambridge Common contract to Newport Construction.

----------------------------------------------------------------------

September 19, 2013

Final construction plans are under development. The Massachusetts Department of Transportation anticipates placing the project out to bid during the fall of 2013. Construction is anticipated to begin in the spring of 2014. The project is anticipated to take approximately 24 months to complete. Access to the playground as well through the Cambridge Common is expected to be maintained during the period of work, with some pedestrian detours as paths are reconstructed. Most events and sporting activities will need to be relocated during construction.

Crews will mobilize on Massachusetts Ave near Garden St on Thursday, June 12 to begin roadway reconstruction and installation of the new multi-use path through Flagstaff Park.  Work in this area will take about 2-3 months to complete.

Improvements within the Common will begin in mid-July and will continue into the fall.  Crews will suspend construction activities within the Common for the winter and will resume in the spring of 2015.

Overall construction is expected to last about 18-24 months.  This includes work within the Common, improvements on Massachusetts Ave and Flagstaff Park.

Please check back for additional schedule information.

Cambridge Common is a National Historic Landmark. Its long and colorful history, connecting it with seventeenth century New England settlement, the Revolutionary War, and regional nineteenth and twentieth century events and trends, make it an important place and tourist attraction.

The Common is also one of the city's major parks. It contains a popular tot lot (which was recently re-built with a $500,000 renovation), youth soccer and other passive activities on its 16 acres. It is a haven for neighborhood people who want a place to relax in the sun or on a bench under a tree. The Common is also significant in that over 10,000 pedestrians and cyclists pass through it on a daily basis.

The Cambridge Common underwent its last significant reconstruction in 1974. At the present time, many elements of the Common need significant work, including broken pathway paving, missing and broken lighting, poor drainage, excess paving, older benches and trash cans, gaps in the tree canopy and older plantings.

A history of changes to the Common was compiled by the city’s Historical Commission and can be by going to the documents tab.

Pedestrian and bicycle travel through this area can be difficult because of the amount of vehicle traffic and past reconfigurations of the roadway to accommodate an underpass constructed under the Harvard campus at Peabody and Cambridge streets and the MBTA bus tunnel at Flagstaff Park. Peabody Street and Garden Street are too narrow for bicycle lanes, and the volume and nature of how traffic flows around the Common makes it difficult for cyclists. At present, the primary travel routes for pedestrians and cyclists wanting to travel from Harvard Square to Mass. Avenue northbound are through the north yard of the Harvard campus or through the Common but these routes may not best serve people depending on their exact starting and ending points.

Because of the complex travel patterns in the area, the Common's function as a travel corridor is being improved through small changes. Minor pathway realignments and other pathway changes are being made to reflect actual pedestrian and bicycle travel patterns and to minimize conflict between the two travel modes. In general, pathway widths are staying the same, except where minor widening is being done to make paths a consistent width.

Concerns about pedestrian/bicycle conflict on shared-use paths in and around the Common have been discussed in depth through several public forums over the years. Representatives of the Pedestrian Committee, the Bicycle Committee, Committee on Public Planting, Historical Commission, Harvard University, Cambridge Office of Tourism, and representatives of the various City departments (including Community Development; Traffic, Parking, and Transportation; Public Works; Police; and the City Manager's Office) reached an agreement several years ago that pedestrians and cyclists should both be accommodated on the Common with this renovation proposal.

As part of the Harvard Square Design Study completed in 2004, the lack of a good bicycle and pedestrian connection through Flagstaff Park was noted as a major impediment to travel between Harvard Square and North Mass. Avenue. The study recommended a multi-use path connection through Flagstaff Park be designed to create a direct and safe connection along the north-eastern edge of Mass. Avenue opposite the Common.

 

  • Cambridge Common

City of Cambridge
Department of Public Works
147 Hampshire Street
Cambridge, MA 02139

Office hours are Mondays, 8:30 AM to 8 PM
Tuesday through Thursday, 8:30 AM to 5 PM
Fridays, 8:30 AM to 12 noon

For additional information or assistance, please contact  Kelly Dunn, Community Relations Manager, at 617.349.4870 or kdunn@cambridgema.gov.

For 24-hour emergency assistance please call Public Works at 617.349.4800.

How can we help you? I'd like...

Mobile Cambridge

Keeping you connected wherever you are. Learn more about Mobile Cambridge

FAQ's

Have a question?
Find the answer in our extensive
Frequently Asked Questions

Dept of Public Works

147 Hampshire St
Cambridge MA 02139

Phone:617.349.4800
TDD:617.499.9924

Hours of Service

Monday: 8:30am-8:00pm
Tuesday-Thursday: 8:30am-5:00pm
Friday: 8:30am-12 noon
24 Hour emergency 617.349.4860

RECYCLING CENTER HOURS

Tuesday & Thursday: 4:00pm-7:30pm
Saturday: 9:00am-4:00pm

Owen O'Riordan
Commissioner