Porter/Harding Streets

The Porter/Harding work is part of the City’s 5-Year Plan for Street and Sidewalks and will include paving, sidewalk work, and pedestrian ramp installations on Porter and Harding streets.

The goal, in addition to the resurfacing of the roadways, is to improve conditions within the public right-of-way for all users, including pedestrians, bicyclists and those with disabilities. The design shall incorporate sidewalks, curb-cuts, curb extensions and crosswalks in compliance with the MassDOT, formerly Massachusetts Highway Department (MHD), Guidelines for Wheelchair Road and Pedestrian Access and the Massachusetts Architectural Access Board Regulations. Also, the design may include traffic calming tools and exclusive pedestrian and/or bicycle facilities.

February 2018:

Street and sidewalk construction will resume in Spring 2018. More information will be available once the contractor releases a construction schedule.


Porter & Harding Streets Project - October 6, 2017
Curb and sidewalk work to begin on or about Tuesday, October 10th

As part of the ongoing street and sidewalk reconstruction work on Porter and Harding streets, the City’s contractor, Newport Construction, will mobilize on or about Tuesday, October 10th to begin curb and sidewalk work.  Crews will remove the sidewalks, remove and reset curbing, and then install new sidewalks. 

This work is expected to take approximately 4 weeks to complete, weather permitting.

At the end of each day, the contractor will clean the work site to allow for motorists to utilize the roadway.

If time and weather allows, final roadway paving will be scheduled and announced via an additional notice in the coming weeks once curb and sidewalk work is complete before the end of this construction season.  If not, final paving will occur in the spring.

What to Expect During Construction:

  • General work hours will be 7am – 4pm, Monday-Friday.
  • Please check posted No Parking signs.
  • Please follow pedestrian detour signs.
  • Access to properties will be maintained, when possible.
  • Access will be maintained for emergency vehicles and City services.

Information & Assistance:

Questions regarding this project?  Contact Dan Riviello, Community Relations Manager, at 617.349.4825/ driviello@cambridgema.gov or Brian McLane, Engineer, at 617-945-4084.  For more information about the project and to sign up for the project email list, visit www.CambridgeMA.gov/theworks/PorterHarding.  If you have any special need or disability, please contact us to arrange for special accommodations that may be necessary.


Porter & Harding Streets Project - June 23, 2017
Full-depth roadway reconstruction to begin or or about Monday, August 7th

As part of the street and sidewalk reconstruction work scheduled for Porter and Harding streets, the City’s contractor, Newport Construction, will begin full-depth roadway reconstruction on or about Monday, August 7th, 2017 to ensure that the roadway conditions will be favorable for many years to come.

This work is expected to take approximately 1 week to complete.

At the end of each day, the contractor will clean the work site to allow for motorists to utilize the roadway. We kindly ask that motorists drive through the construction zone slowly outside of general working hours. Final roadway paving will be scheduled and announced via an additional notice in the coming weeks.

What to Expect During Construction:
• General work hours will be 7am – 4pm, Monday-Friday.
• Please check posted No Parking signs.
• Please follow pedestrian detour signs.
• Access to properties will be maintained, when possible.
• Access will be maintained for emergency vehicles and City services.

Information & Assistance:
Questions regarding this project? Contact Dan Riviello, Community Relations Manager, at 617.349.4825/ driviello@cambridgema.gov or Brian McLane, Engineer, at 857-829-8597. For more information about the project and to sign up for the project email list, visit www.CambridgeMA.gov/theworks/PorterHarding. If you have any special need or disability, please contact us to arrange for special accommodations that may be necessary.


Porter & Harding Streets Project - June 23, 2017
Water services work to begin in the coming weeks

As part of the street and sidewalk reconstruction work scheduled for Porter and Harding streets, the City’s contractor, Newport Construction, will begin to replace select lead water services in the coming weeks.

This work is expected to take approximately 4 weeks to complete, and affected property owners will be notified by the Cambridge Water Department.

If you believe you may have a lead service but have not been contacted by the Water Department, please contact the CWD at 617-349-4770 or email mgallagher@cambridgema.gov.

What to Expect During Construction:
• General work hours will be 7am – 4pm, Monday-Friday.
• Please check posted No Parking signs.
• Please follow pedestrian detour signs.
• Access to properties will be maintained, when possible.
• Access will be maintained for emergency vehicles and City services.

Information & Assistance:
Questions regarding this project? Contact Dan Riviello, Community Relations Manager, at 617.349.4825/ driviello@cambridgema.gov or the Department of Public Works at 617-349-4800. For more information about the project and to sign up for the project email list, visit www.CambridgeMA.gov/theworks/PorterHarding. If you have any special need or disability, please contact us to arrange for special accommodations that may be necessary.


April 2017

Crews completed drainage work on Porter and Harding Streets.


Porter & Harding Streets Road/Sidewalk Work - January 31, 2017
Community meeting scheduled for Wednesday, February 8th

As part of the street and sidewalk reconstruction work scheduled for spring 2017, the City’s contractor, Newport Construction, will begin drainage work in the roadway during the week of February 6, 2017.

This first phase of utility work is expected to last for approximately 4 weeks, weather permitting, and general work hours will be 7am-4pm, Monday-Friday. “No Parking” signs will be posted, so please be sure to check posted signs to avoid being ticketed/towed. The roadway and sidewalk reconstruction is anticipated to begin this summer and last approximately 3-4 months.

The Porter/Harding street and sidewalk reconstruction work is part of the City’s 5-Year Plan for Street and Sidewalks and will include paving, sidewalk work, and pedestrian ramp installations on Porter and Harding streets.

We invite you to attend a community meeting with your neighbors and members of the Department of Public Works on Wednesday, February 8th, from 6-7:30pm in the community room of the Millers River Apartments located at 15 Lambert St. to learn more about this project, its scope, and anticipated schedule. Please enter through the Cambridge St. entrance between Warren St. and Max Ave. At the meeting we will also be discussing:

  • Back of Sidewalk Tree Planting Program
    • The term “Back of Sidewalk" refers to the edge of the sidewalk where public way meets private properties. In the case of this program, the City will plant trees along the back of sidewalk, (up to 20 feet off the public way) on private property of interested, eligible owners.
  • Sidewalk material options
    • It is the City’s policy to replace existing sidewalks with the same material (concrete with concrete, brick with wire cut brick). However, during this project, property owners will have the option of changing their sidewalk material for a fee if they choose. More information will be made available to residents.

Information & Assistance:

Questions regarding this project? Contact Dan Riviello, Community Relations Manager, at 617.349.4825/ driviello@cambridgema.gov or the Department of Public Works at 617-349-4800. For more information about the project and to sign up for the project email list, visit www.CambridgeMA.gov/theworks/PorterHarding. If you have any special need or disability, please contact us to arrange for special accommodations that may be necessary.
The Porter/Harding streets work is part of the City’s 5-Year Plan for Street and Sidewalks and will include paving, sidewalk work, and pedestrian ramp installations on Porter and Harding streets.

Work to resume Spring 2018. Please visit the Updates tab for the most up-to-date information and schedule for this project.


Project to begin in winter 2017.

Brian McLane

Project Manager

Phone: 617-349-4824

Email: bmclane@cambridgema.gov


Dan Riviello

Community Relations Manager

Phone: 617-349-4825

Email: driviello@cambridgema.gov

Sign up for Email Updates

How can we help you? I'd like...

Service Requests

Commonwealth Connect Promo

Cambridge citizen requests, now online & on the go! Report issues here.

FAQ's

Have a question?
Find the answer in our extensive
Frequently Asked Questions

Dept of Public Works

147 Hampshire St
Cambridge MA 02139

Phone:617.349.4800
TDD:617.499.9924

Hours of Service

Monday: 8:30am-8:00pm
Tuesday-Thursday: 8:30am-5:00pm
Friday: 8:30am-12 noon
24 Hour emergency 617.349.4860

RECYCLING CENTER HOURS

Tuesday & Thursday: 4:00pm-7:30pm
Saturday: 9:00am-4:00pm

Owen O'Riordan
Commissioner