Weekly Construction Highlights

Construction for the week of July 28, 2014

Amory Street
The Cambridge Water Department is scheduled to continue work on Amory Street during the week of August 3.

Broadway Improvements (Third Street to Ames Street)
There is no scheduled work this week.

Broadway Reconstruction Project (Portland Street to Prospect Street)
There is no scheduled work this week.

Cambridge Street Tunnel
Crews have mobilized to the area to replace the 2” concrete overlay in the Cambridge Street Tunnel. The concrete overlay, which was installed in the summer of 2013, did not bond properly with the floor of the tunnel and began failing last fall. Over the winter and spring, sections of the overlay deteriorated and had to be replaced with temporary asphalt patches. Next week, the contractor will begin to remove the 2” concrete overlay, make any necessary repairs to the concrete base and then place the new concrete wearing surface. The work will be done in phases to maintain one travel lane in each direction of the tunnel, and is expected to be completed by September 2014

Cambridge Common
Crews are currently performing work inside of the Cambridge Common.

Concord Ave Project
There are three crews in the project area this week. There is one crew on Concord Avenue performing sewer and drain work. The other two crews are on Ivy Street and Corporal Burns Road performing water tie-ins and drainage.

Huron A Project 
Crews are performing sidewalk work on Lakeview Ave, Vassal Lane and Lexington Ave.

Huron B Project
This week, there will be several crews in the area:

Crew #1 - Performing sewer work at the corner of Huron Ave and Lakeview Ave
Crew #2 - Engaged in water lateral work on Blakeslee
Crew #3 - Sewer work on Fayerweather Street
Crew #4 - Coordinate temporary water on Vassal Lane
Crew #5 - Water testing on Chilton Street
Crew #6 - Performing Drainage work on Saville Street

Fawcett Street
Final roadway paving is scheduled for Tuesday, July 29.

Garden Street (no link)
During the week of July 28, the city's contractor will be on site to resume the sidewalk reconstruction on Garden Street. The work is scheduled to be completed within 2 weeks. General work hours will be 7 AM to 4 PM, Monday through Friday and crews will begin construction activity at 9am when working near the Walden Street intersection.

Irving Street/Scott Street Construction
The final roadway paving is scheduled for August 2014.

Longfellow Road Reconstruction Project
This week, crews will be tree pruning and performing tree removals. Crews will also be performing sidewalk work on the east side of Longfellow Road. Longfellow Road will be closed on most week days during general hours (Monday thru Friday, 7am-4pm).

Main Street
On Tuesday, July 29, the city’s contractor, Newport Construction, will begin construction of the Third Street Connector between Main St and Broadway. During this phase, access to Main St from Broadway will be closed while crews construct the new vehicular connection (see detour map attached). MBTA Bus, shuttle and trolley stops on Main St will not be affected by the Third St Connector construction. This phase is expected to take about 2 months to complete.

Massachusetts Avenue
This week, there will be two crew on site. One crew will be performing work at the corner Mass Ave at Shepherd Street. Crews are also pouring sidewalks on the corner of Mass Ave and Creighton Street.

Mt. Auburn Street
On Saturday, August 2 (weather permitting), the City’s contractor, D’Allessandro Corporation, will mobilize on Mt. Auburn Street between Gibson St and the Fresh Pond Parkway, to begin surface improvements. The scope of work includes the reconstruction of reconstructed sidewalks with several curb extensions and new roadway paving. We expect the work to take about 2 ½ months to complete.

Tufts Street
Tufts Street is scheduled to be paved during the week of August 4, 2014.

Waverly Path
The contractor is mobilizing this week to set up the work zone and to perform tree protection in the area.

Western Ave Reconstruction Project
This week, two crews continue to work on sidewalks and the roadway from Soden Street to Dodge Street. Another crew is located at Cronin Park for renovations. 

More information on all city construction projects.

How can we help you? I'd like...

Mobile Cambridge

Keeping you connected wherever you are. Learn more about Mobile Cambridge

FAQ's

Have a question?
Find the answer in our extensive
Frequently Asked Questions

Dept of Public Works

795 Massachusetts Ave
Cambridge MA 02139

Phone:617.349.4000
TDD:617.349.4242

Hours of Service

Monday: 8:30am-8pm
Tuesday-Thursday: 8:30am-5pm
Friday: 8:30am-12pm