Weekly Construction Highlights

Construction for the week of November 10, 2014

         Sidewalk Reconstruction

Amory Street
The Cambridge Water Department will be installing new water services this week from St. Mary Road to Hampshire Street.

Cambridge Park Drive (no link)
Roadway paving is scheduled for Tuesday, November 4 (weather permitting).

Cambridge Street Tunnel
Crews have mobilized to the area to replace the 2” concrete overlay in the Cambridge Street Tunnel. The concrete overlay, which was installed in the summer of 2013, did not bond properly with the floor of the tunnel and began failing last fall. Over the winter and spring, sections of the overlay deteriorated and had to be replaced with temporary asphalt patches. The work will be done in phases to maintain one travel lane in each direction of the tunnel, and is expected to conclude in November 2014.

Cambridge Common
Crews will not be working on Monday, November 10 and Tuesday, November 12. For the remainder of the week, the contractor will focus on handicap ramps and granite curbing at Flaggstaff Park.

Concord Ave Project
There will be several crews in the area:

Crew #1 -   Contract Area – Test Pits / Pre-construction activity
Crew #2 -  Birch- Test Pits
Crew #3 -  Copley- Water and catch basin installation
Crew #4 -  Fayerweather- Catch basin installation
Crew #5 -  Fern- Test Pits
Crew #6 - Walden (Copley to Concord)- Drain and Sewer and catch basins

Fulkerson Street
This week, crews will continue with drainage work at the corner of Fulkerson Street and Otis Street.

Harvard Square Public Toilet
Newport Construction, the City's contractor, will be performing utility work in advance of the installation of the Harvard Square public toilet.

Huron A Project 
There are 5 crews in the area performing sidewalk work:

Crew #1 - Lakeview (South)- Brick sidewalk installation
Crew #2 - Larch (North)- Curb and sidewalk
Crew #3 - Lexington (South)- Brick sidewalk installation
Crew #4 - Standish- Curb and sidewalk
Crew #5-  Tobin School- Catch basin repair

Huron B Project
This week, there will be several crews in the area:

Crew #1 -   Blakeslee- Drain and sewer
Crew #2 -  Chilton- Curb installation
Crew #3 -  Fayerweather- Temporary paving
Crew #4 -  Huron (Chilton to Lexington)- Temporary paving
Crew #5 -  Huron - Drain laterals
Crew #6 -  Project wide- Private inflow
Crew #7 - Reservoir- Temporary paving
Crew #8 - Royal- Drain laterals
Crew #9 - Vassal (Alpine to Huron)- Sewer and drain

Monday, Nov 10th* - Huron Ave (Lexington to Chilton): Milling and Paving
Reservoir Street (Vassal to Fayerweather): Milling and Start Paving

Wednesday, Nov 12th*- Reservoir Street (Vassal to Fayerweather): Complete Paving
Fayerweather Street (Huron to Reservoir): Milling and Paving

*Please note paving is weather dependent. In the event of inclement weather, call 617-498-4719 for more information.


Irving Street/Scott Street Construction
Final roadway paving has been completed. We are currently working with the contractor to finalize a date for line striping.

Main Street
The City's contractor, Newport Construction, continues to reconnect the water main and administer tests to ensure that the water main upgrade has no issues.

Massachusetts Avenue
This week, crews will be construction raised crosswalks on Russell Street at Mass Ave, Hadley Street at Mass Ave, and Blakeslee at Mass Ave. There is no work scheduled on Mass Ave between Shepard Street and Linnaean St. Crews have cleaned up and left the area.

Mead Street
The sewer main has been completed and the roadway and sidewalk restoration phase of the project will take place in spring/summer 2015.

Mt. Auburn Street
NStar Gas crews continue work on the relocation of the gas main at the intersection of Longfellow Road and Mt. Auburn Street. Crews anticipate leaving the area later this week.

Waverly Path
Landscaping is scheduled to take place this week.

Western Ave Reconstruction Project
There will be several crews on site this week working on the north side sidewalks and roadway on Western Avenue between Soden and Howard Street and between Riverside Place and Memorial Drive. While crews work near the Memorial Drive intersection, Western Avenue will be reduced to 2 lanes of travel during general work hours (7am-4pm, Monday through Friday). This work is expected to be completed this week. Crews will be working on Tuesday, November 11 (Veterans' Day) 

 

More information on all city construction projects.

How can we help you? I'd like...

Mobile Cambridge

Keeping you connected wherever you are. Learn more about Mobile Cambridge

FAQ's

Have a question?
Find the answer in our extensive
Frequently Asked Questions

Dept of Public Works

795 Massachusetts Ave
Cambridge MA 02139

Phone:617.349.4000
TDD:617.349.4242

Hours of Service

Monday: 8:30am-8pm
Tuesday-Thursday: 8:30am-5pm
Friday: 8:30am-12pm