City Construction Projects Update

caution sign The information on this page may be outdated as it was published 3 years ago.

Photo of two construction cones with construction workers in the background

On March 18th, Cambridge issued a Temporary Emergency Construction Moratorium to limit construction in the City to help prevent the spread of COVID-19. Last week, the City issued an Amended Temporary Emergency Construction Order to allow construction to restart in a phased approach in the coming weeks.

What does this mean for construction in my neighborhood?

Beginning this week, you may start to see some construction activity related to site safety preparations, including installation of hand wash stations and other site modifications related to COVID-19 safety precautions. Beginning June 1st, you may start to see increased activity on your street related to the re-starting of construction. We will be in touch via additional notices with a schedule and information specific to the project on your street.

Residents should be aware that No Parking signs will start to appear in relation to construction activity. Contractors will make every effort to provide 48-hours’ notice, but please check the street frequently.

Help Us Spread the Word!
We will not be distributing paper notices to each location at this time. Please encourage your neighbors to sign up to receive email notifications about projects around the City at cambridgema.gov/subscribe.

COVID-19 Control Plan for Construction:

In addition to the stringent safety guidelines required by the State, all contractors will need to submit to the Inspectional Services Department or Department of Public Works, as appropriate, a COVID-19 Control Plan for Cambridge on permitted projects. This plan will require:

  • A cleaning and decontamination checklist; The number of workers expected on the job site; and
  • No non-essential personnel may be present at the worksite.
  • Additionally, contractors will be encouraged, and in some cases required, to conduct a site-specific risk analysis and enhanced COVID-19 safety plan for more complex projects.

As previously announced on May 18, the City of Cambridge will expand currently allowed construction activity in the City in four phases:

  • Phase 1, beginning May 25, will add site safety prep work for projects previously permitted by Inspectional Services (ISD) and Public Works (DPW). Forthcoming amendments to the City’s Temporary Emergency Construction Order issued on March 18 will modify the definition of essential construction to include work associated with COVID-19 restaurant modification needed to allow them to safely reopen;
  • Phase 2, beginning on June 1, will add horizontal construction, city building projects, 100% affordable housing developments, larger buildings (over 25,000 square feet) previously permitted by ISD or DPW;
  • Phase 3, tentatively beginning on June 15, will add all remaining existing construction previously permitted by ISD and DPW; and
  • Phase 4, tentatively beginning on June 29, will add new permits. Permits can be submitted, and pre-reviews will occur at any time, but permits will not be formally accepted or issued until this date.

    For additional details on the Amended Temporary Emergency Construction Order, please click here.
     

Page was posted on 6/1/2020 12:53 AM
Page was last modified on 7/25/2023 3:40 AM
Contact Us

How can we help?

Please provide as much detail below as possible so City staff can respond to your inquiry:

As a governmental entity, the Massachusetts Public Records Law applies to records made or received by the City. Any information received through use of this site is subject to the same provisions as information provided on paper.

Read our complete privacy statement


Service Requests

Enter a service request via SeeClickFix for things like missed trash pickups, potholes, etc., click here