As part of the Municipal Facilities Improvement Plan, the Taylor Square Firehouse will be undergoing several improvements beginning in Spring 2019. This construction is anticipated to take 12 months to complete. The firehouse crew will be relocated during the construction. 

Construction Notice: Exploratory work taking place on Friday, May 17

This Friday, 5/17/19 our contractor, Boston Building and Bridge, will be on site at the Taylor Square Fire House to dig a test well for the geothermal wells that are part of the larger construction project beginning in August 2019. The location of the test well is on the apron in front of the left overhead door. It is anticipated this work will take approximately 8 hours.


Community Meeting Notice: Taylor Square Firehouse Alteration Project, Cambridge Main Library, 449 Broadway, Lower Level Auditorium, Parking is available for a small fee in the library garage. Tuesday, January 29, 2019, 7:00-8:00 PM

On Tuesday, January 29, 2019 from 7:00-8:00pm, the Department of Public Works will be hosting a Community Meeting in the Lower Level Auditorium at the Cambridge Main Library located at 449 Broadway.
City staff will be holding a public meeting to discuss alterations to the Taylor Square Firehouse at 113 Garden Street. Construction is anticipated to begin in Spring 2019 and last approximately 12 months.
The project generally consists of:
  • Roof replacement including a 24kW solar photovoltaic array
  • Ground source heat pumps including drilling three new wells at the firehouse apron.
  • Upgrade to the electrical service, including the emergency generator
  • Second floor window replacement
  • Painting exterior trim
  • Accessibility upgrades for public access
  • Masonry work at rear egress stair
  • Interior water and electrical saving measures
It is necessary to temporarily relocate the Taylor Square Firehouse crew in order to complete this work. A nearby site has been selected, which provides allowable response times to this firehouse’s normally assigned response area.

A brief presentation will be given, followed by a comment, question and answer period. We encourage you to attend, as we value the feedback we receive from Cambridge residents and businesses.
Information and Assistance:
The City of Cambridge does not discriminate on the basis of disability. The City of Cambridge will provide auxiliary aids and services, written materials in alternative format, and reasonable modifications in policies upon request. For more information on this project, please contact Julie Lynch at the Department of Public Works at jlynch@cambridgema.gov / 617.349.9452.

Construction is scheduled to begin in Spring 2019 and will last for approximately 12 months. 

The City recently initiated a Municipal Facilities Improvement Plan, which evaluated and prioritized 43 buildings for capital improvements in areas such as accessibility, climate resilience, building envelope, fire and life safety, historic preservation, heating, ventilation, and air conditioning (HVAC), lighting, occupant comfort, and mechanical systems. Beginning in FY2016 this Department of Public Works program has completed: HVAC upgrades at the East Cambridge Firehouse, Robert W. Healy Public Safety Facility, the Main Library and Central Square Library; rooftop photovoltaic solar arrays at the Kennedy Longfellow School, Citywide Senior Center, Fletcher Maynard Academy and Main Library; roof replacement projects at the Citywide Senior Center, Moore and Moses Youth Centers; interior alteration projects at the Coffon Lower Level, City Hall Annex, and DPW Frazier Building; accessibility upgrades across multiple buildings, and other improvement projects.  As part of the plan for FY 2019, the Taylor Square Firehouse will undergo renovations consisting of:

  • Roof replacement including a 24kW solar photovoltaic array
  • Ground source heat pumps including drilling three new wells at the firehouse apron.
  • Upgrade to the electrical service, including the emergency generator
  • Second floor window replacement
  • Painting exterior trim
  • Accessibility upgrades for public access
  • Masonry work at rear egress stair
  • Interior water and electricity saving measures

It is necessary to temporarily relocate the Taylor Square Firehouse crew in order to complete this work. A nearby site has been selected, which provides allowable response times to this firehouse’s normally assigned response area.




How can we help you? I'd like...

Service Requests

Commonwealth Connect Promo

Cambridge citizen requests, now online & on the go! Report issues here.

FAQ's

Have a question?
Find the answer in our extensive
Frequently Asked Questions

Dept of Public Works

147 Hampshire St
Cambridge MA 02139

Phone:617.349.4800
TDD:617.499.9924

Hours of Service

Monday: 8:30am-8:00pm
Tuesday-Thursday: 8:30am-5:00pm
Friday: 8:30am-12 noon
24 Hour emergency 617.349.4860

RECYCLING CENTER HOURS

Tuesday & Thursday: 4:00pm-7:30pm
Saturday: 9:00am-4:00pm

Owen O'Riordan
Commissioner