New Street Infrastructure and Streetscape Improvements and Concord Lane Sewer Separation Project

Surface improvements from Bay State Rd to the railroad tracks

Upcoming Work Activity

Week of October 23rd – October 27th
Activity Description:

• Concord Lane – Miscellaneous punch list items
• New Street – Miscellaneous punch list items

Streets Impacted: Concord Lane, New Street

Week of October 30th – November 3rd (anticipated activity)
Activity Description:

• Concord Lane – Miscellaneous punch list items
• New Street – Miscellaneous punch list items

Streets Impacted: Concord Lane, New Street

Resident Engineer: Ray Elie at (978) 427-4837 / RElie@kleinfelder.com

Contact Information:
For any questions, concerns, or assistance with this project, or to sign up to receive project
specific email updates, please contact KyAnn Anderson, Community Relations Manager, at (617) 498-4708 / kanderson@kleinfelder.com.

In case of emergency after hours or on weekends, please call the DPW 24-Hour line at (617)-349-4800.

Parking Notifications:
For on-going construction zones, we aim for “No Parking” signs to be posted 48 hours advance; however, with changing schedules; coordination with private utility companies; and unexpected conditions; that isn’t always possible. A minimum of 24 hours advance notice is required in on-going construction zones. We encourage residents parking in, or adjacent to, on-going construction zones to leave a key with a friend or neighbor if leaving for more than 24 hours.

















Street and sidewalk restoration for New Street and Concord Lane is tentatively scheduled to begin Spring 2016.

The streetscape improvements for New Street were developed through a community process focused on making improvements to pedestrian and bicycle access; reconstructing the deteriorate roadway; and. enhancing the area with new street trees.

The New Street streetscape improvements will be constructed under a contract that will include sewer separation work on Concord Lane and pump station improvement work on New Street. This contract was awarded to Barletta Heavy Construction in March 2015.


For more information about this project, please contact Elise Curley, Community Relations Representative at 617.498.4719/ ecurley@kleinfelder.com or Catherine Day Woodbury, Project Manager at 617.349.4818/ cwoodbury@cambridgema.gov.

How can we help you? I'd like...

Service Requests

Commonwealth Connect Promo

Cambridge citizen requests, now online & on the go! Report issues here.

FAQ's

Have a question?
Find the answer in our extensive
Frequently Asked Questions

Dept of Public Works

147 Hampshire St
Cambridge MA 02139

Phone:617.349.4800
TDD:617.499.9924

Hours of Service

Monday: 8:30am-8:00pm
Tuesday-Thursday: 8:30am-5:00pm
Friday: 8:30am-12 noon
24 Hour emergency 617.349.4860

RECYCLING CENTER HOURS

Tuesday & Thursday: 4:00pm-7:30pm
Saturday: 9:00am-4:00pm

Owen O'Riordan
Commissioner