Concord Avenue Neighborhood

The Concord Ave Project includes the streets listed below. To view streetscape plans, please click on one of the 4 general areas in the table below.

2017 Updated Streetscape Plans

Northeast Area Northwest Area South Area Concord Avenue
Chilton St. (N. of Concord Ave) Alpine St. (N. of Concord Ave) Alpine St. (S. of Concord Ave)
Copley Street Bay State Road Chilton St. (S. of Concord Ave)
Fayerweather St. (N. of Concord Ave) Birch Street Fayerweather St. (S. of Concord Ave)
Field Street (East of Alpine St.) Corporal Burns Road Saville Street
Hazel Street Fern Street
Ivy Street Field Street (W. of Alpine St.)
Walden Street Garden Street
Upcoming Activity:
  • Project wide installation of planting areas, tree plantings, biobasin, trench drain at library, and bike rings scheduled to begin in March 2017.
  • Sign installation project wide to begin March 2017.
  • Sidewalk and crosswalk work to resume March 2017.
  • Installation of artscape and multi-use path on Fern Street to begin in April 2017 and continue through May 2017.
  • Final paving and pavement markings on Concord Ave and remaining side streets beginning in May 2017 and continue through June 2017.
  • Porous pavement installation in June 2017.


Alewife Sewer Separation Project - Construction Update for August/September 2016

View this week's traffic map

NOTE:  For paving schedule updates, please call 617-498-4704.

Week of June 26th – June 30th
Activity Description:

• Chilton (Concord to Vassal) – Porous paving
• Copley – Porous paving
• Fayerweather – Porous paving
• Field – Porous paving
• Saville (Fayerweather to Walden) – Porous paving
• Walden – Porous paving
• Project wide – Miscellaneous landscaping activities
• Project wide – Miscellaneous sidewalk work
• Project wide – Permanent lane striping
Streets Impacted: Chilton Street, Copley Street, Fayerweather street, Field Street, Saville Street, Walden Street 

Week of July 3rd – July 7th (anticipated activity)*
*Note: There will be no construction activity on the July 4th holiday.
Activity Description:

• Chilton (Concord to Vassal) – Porous paving
• Copley – Porous paving
• Fayerweather (Walden to Concord) – Porous paving
• Field – Porous paving
• Saville (Fayerweather to Walden) – Porous paving
• Walden – Porous paving
• Project wide – Miscellaneous landscaping activities
• Project wide – Miscellaneous sidewalk work
• Project wide – Permanent lane striping
Streets Impacted: Chilton Street, Copley Street, Fayerweather street, Field Street, Saville Street, Walden Street
  
Resident Engineer: Mike Smith at (857) 201-1005 / Michael.d.smith@mwhglobal.com

Contact Information:
For any questions, concerns, or assistance with this project, or to sign up to receive project
specific email updates, please contact KyAnn Anderson, Community Relations Manager, at (617) 498-4708 / kanderson@kleinfelder.com
In case of emergency after hours or on weekends, please call the DPW 24-Hour line at (617)-349-4800.

Parking Notifications:
For on-going construction zones, we aim for “No Parking” signs to be posted 48 hours advance; however, with changing schedules; coordination with private utility companies; and unexpected conditions; that isn’t always possible. A minimum of 24 hours advance notice is required in on-going construction zones. We encourage residents parking in, or adjacent to, on-going construction zones to leave a key with a friend or neighbor if leaving for more than 24 hours.

April 2017

Click here for the latest community schedule.

Concord Avenue Neighborhood Contract Overall Schedule:
• Preliminary Design: January 2013 – May 2013
• Final Design: June 2013 – September 2013
• Construction Begins* winter 2013/2014





PROJECT BACKGROUND

The Alewife Sewer Separation Project is made up of three major contract areas in three adjoining neighborhoods, the Huron Avenue A, Huron Avenue B and Concord Avenue neighborhoods. These contracts are part of the Massachusetts Water Resources Authority’s (MWRA) Long Term Combined Sewer Overflow (CSO) Control Plan for the Alewife Brook. Sewer separation and stormwater management in these contract areas will separate existing combined sewers and provide dedicated sanitary sewers and stormwater drains.

About The Design

The principal goals of the Alewife Sewer Separation Project is to improve water quality in the Alewife Brook by eliminating combined sewer overflows; protect Fresh Pond Reservoir from potential contaminants; and, control the occurrences of street flooding and sewer and stormwater backups on public and private properties. Prior to beginning design, building and system investigation for the entire project area was undertaken by the City’s consultants. Those Investigations are necessary to understand how and where discharges from the sanitary sewer, sump pump, yard drain, driveway drain, stairwell drain and roof drains leave private property. In addition to the sewer separation work, the infrastructure design for each project area will include upgrades of water, cable, gas and electric.

The City will work with the community in developing an approach to surface improvements that address pedestrian, vehicular, landscaping, and environmental concerns for each of the project areas. Community meetings will be held to discuss neighborhood concerns and potential design solutions.

Cambridge Department of Public Works
147 Hampshire Street
Catherine Daly Woodbury, Project Manager
cwoodbury@cambridgema.gov / 617.349.4818

DPW Office hours are:
Mondays, 8:30 AM to 8 PM
Tuesday through Thursday, 8:30 AM to 5 PM
Friday, 8:30 AM to 12 noon

For information related to the project design and to sign up to receive project specific email updates contact KyAnn Anderson, the DPW's Community Coordinator at 617.498.4708/ Kanderson@kleinfelder.com or Catherine Daly Woodbury the DPW's Project Manager at 617.349.4818/ cwoodbury@cambridgema.gov .

How can we help you? I'd like...

Service Requests

Commonwealth Connect Promo

Cambridge citizen requests, now online & on the go! Report issues here.

FAQ's

Have a question?
Find the answer in our extensive
Frequently Asked Questions

Dept of Public Works

147 Hampshire St
Cambridge MA 02139

Phone:617.349.4800
TDD:617.499.9924

Hours of Service

Monday: 8:30am-8:00pm
Tuesday-Thursday: 8:30am-5:00pm
Friday: 8:30am-12 noon
24 Hour emergency 617.349.4860

RECYCLING CENTER HOURS

Tuesday & Thursday: 4:00pm-7:30pm
Saturday: 9:00am-4:00pm

Owen O'Riordan
Commissioner