Huron A Improvements

 

Includes, Larch Rd, Grozier Rd, Lexington Ave, Lakeview Ave, Standish St, Vassal Lane (Lakeview to Standish), Malcolm Road, Hawthorne Park

Week of April 22-25

Activity Description:
• Grozier (North/South) – Curbs and sidewalks
• Huron (Gurney to Standish) – Water main testing
• Lakeview (North) – Road reconstruction
• Lakeview (South) – Sewer
• Tobin School – Temporary drives/sidewalk removal

Streets Impacted: Grozier Road, Huron Avenue, Lakeview Avenue

NSTAR Gas
• Crew 1 – Alpine (Field to Concord)
• Crew 2 – Fayerweather (Vassal to Huron)
• Crew 3 – Appleton (Brattle to Dunstable)
• Crew 4 – Fayerweather (Reservoir to Huron)
• Crew 5 – Corporal Burns

Week of April 28-May 2 (anticipated activity)

Activity Description:
• Grozier (North/South) – Curbs and sidewalks
• Huron (Gurney to Standish) – Water main chlorination/testing
• Lakeview (North) – Paving
• Lakeview (South) – Road reconstruction
• Lexington, Hawthorne, Poplar – Curbs and sidewalks
• Tobin School – Temporary drives/sidewalk removal

Streets Impacted: Grozier Road, Hawthorne Park, Huron Avenue, Lakeview Avenue, Lexington Avenue, Poplar Road

NSTAR Gas
• Crew 1 – Alpine (Field to Concord)
• Crew 2 – Fayerweather (Field to Huron)
• Crew 3 – Appleton, Reservoir, Vassal, Walden
• Crew 4 – Fayerweather (Reservoir to Huron)
• Crew 5 – Corporal Burns

Future Outlook:
• Standish - Road reconstruction

Additional Resident Engineer Notes:
• Paving trenches is ongoing

Resident Engineer: David McCarthy at (617) 833-5890 

Contact Information: For any questions, concerns, or assistance with this project, or to sign up to receive project 
specific email updates, please contact KyAnn Anderson, DPW’s Community Relations Manager, at (617) 498-4708 / kanderson@kleinfelder.com 

In case of emergency after hours or on weekends, please call the DPW 24-Hour line at (617)-349-4800.

January 13, 2014

Construction for the Alewife Sewer Separation Project - Huron A Neighborhood begun in October 2012.  Construction is estimated to last approximately 2+ years and be completed by December 2014.  Click here for an estimated construction schedule for the Huron A project area.

Designs for the three contracts are anticipated to follow the timelines below:

• Huron Ave Contract A – Completed
• Huron Ave Contract B – May 2012 to July 2013
• Concord Ave Contract – March 2013 to September 2013

 Construction for the three contracts is anticipated to follow the timelines below:

• Huron Ave Contract A – September 2012 to December 2014
• Huron Ave Contract B – September 2013 to December 2015
• Concord Ave Contract  – January 2014 to September 2016*

   * NOTE - Sewer separation for Concord Ave is estimated to be completed by September 2016, followed by 9 months of surface restoration and improvements.

 

Project Background

Huron Ave Contract A, Huron Ave Contract B and  the Concord Ave Contract are part of the Massachusetts Water Resources Authority’s (MWRA) Long Term Combined Sewer Overflow (CSO) Control Plan for the Alewife Brook. Sewer separation and stormwater management in these contract areas will separate existing combined sewers and provide dedicated sanitary sewers and stormwater drains.

 

About The Design

The principal goals of this project are to improve water quality in the Alewife Brook by eliminating combined sewer overflows; protect Fresh Pond Reservoir from potential contaminants; and, control the occurrences of street flooding and sewer and stormwater backups on public and private properties. Prior to beginning design, building and system investigation for the entire project area was undertaken by the City’s consultants. Those investigations are necessary to understand how and where discharges from the sanitary sewer, sump pump, yard drain, driveway drain, stairwell drain and roof drains leave private property. In addition to the sewer separation work, the infrastructure design for each project area will include upgrades of water, cable, gas and electric.

The City will work with the community in developing an approach to surface improvements that address pedestrian, vehicular, landscaping, and environmental concerns for each of the project areas. Community meetings will be held to discuss neighborhood concerns and potential design solutions.

 

 

 

Cambridge Department of Public Works
147 Hampshire Street

cwoodbury@cambridgema.gov

Office hours are Mondays, 8:30 AM to 8 PM
Tuesday through Thursday, 8:30 AM to 5 PM
Fridays, 8:30 AM to 12 noon

 

For information related to the project design and construction please contact KyAnn Anderson, the DPW's Community Coordinator at (617) 498-4708/ Kanderson@kleinfelder.com or Catherine Daly Woodbury the DPW's Project Manager at 617.349.4818/ cwoodbury@cambridgema.gov.

 

 

How can we help you? I'd like...

Dept of Public Works

147 Hampshire St
Cambridge MA 02139

Phone:617.349.4800
TDD:617.499.9924

Hours of Service

Monday: 8:30am-8:00pm
Tuesday-Thursday: 8:30am-5:00pm
Friday: 8:30am-12 noon
24 Hour emergency 617.349.4860

RECYCLING CENTER HOURS
Tuesday & Thursday: 4:00pm-7:30pm
Saturday: 9:00am-4:00pm

Visit us on facebook Follow us on twitter

OWEN O'RIORDAN
 COMMISSIONER

   

Cambridge Mobile Apps

Cambridge iReport Promo  
Keeping you connected wherever you are.  Learn more about Mobile Cambridge 

 

FAQ's

Have a question?
Find the answer in our extensive
Frequently Asked Questions