Huron A Improvements

 

Includes, Larch Rd, Grozier Rd, Lexington Ave, Lakeview Ave, Standish St, Vassal Lane (Lakeview to Standish), Malcolm Road, Hawthorne Park

Travel Routes Suggested for the Week of December 15th, 2014

Week of December 15th – December 19th

Activity Description:
• Lakeview (South)- Sidewalk installation
• Lexington (South)- Sidewalk installation, porous trench installation
• Project wide- Miscellaneous ROE work and sign installation

Streets Impacted: Lakeview Avenue and Lexington Avenue



Week of December 22nd – December 26th (anticipated activity)
Please note there is no construction activity December 24th through January 5th

Activity Description:
• Lakeview (South)- Sidewalk installation
• Lexington (South)- Sidewalk installation
• Project wide- Miscellaneous ROE work and sign installation

Streets Impacted: Lakeview Avenue and Lexington Avenue

Future Outlook:
• Waterman Road- Paving in Spring 2015
• Sidewalk and curb installation will continue on designated streets as winter weather allows

Additional Resident Engineer Notes:
• Porous Pavement installation in Spring 2015

Resident Engineer: David McCarthy at (617) 833-5890

Contact Information: 
For any questions, concerns, or assistance with this project, or to sign up to receive project 
specific email updates, please contact KyAnn Anderson, DPW's Community Relations Manager, at (617) 498-4708 / kanderson@kleinfelder.com 

In case of emergency after hours or on weekends, please call the DPW 24-Hour line at (617)-349-4800.

 

September 8, 2014

Construction for the Alewife Sewer Separation Project - Huron A Neighborhood begun in October 2012.  Construction is estimated to last approximately 2+ years and be completed by Spring 2015.  Click here for an updated construction schedule for the Huron A project area.

Designs for the three contracts are anticipated to follow the timelines below:

• Huron Ave Contract A – Completed
• Huron Ave Contract B – Completed
• Concord Ave Contract – Completed

 Construction for the three contracts is anticipated to follow the timelines below:

• Huron Ave Contract A – September 2012 to December 2014
• Huron Ave Contract B – September 2013 to December 2015
• Concord Ave Contract  – January 2014 to September 2016*

   * NOTE - Sewer separation for Concord Ave is estimated to be completed by December 2015, followed by 9 months of surface restoration and improvements.

 

Project Background

Huron Ave Contract A, Huron Ave Contract B and  the Concord Ave Contract are part of the Massachusetts Water Resources Authority’s (MWRA) Long Term Combined Sewer Overflow (CSO) Control Plan for the Alewife Brook. Sewer separation and stormwater management in these contract areas will separate existing combined sewers and provide dedicated sanitary sewers and stormwater drains.

 

About The Design

The principal goals of this project are to improve water quality in the Alewife Brook by eliminating combined sewer overflows; protect Fresh Pond Reservoir from potential contaminants; and, control the occurrences of street flooding and sewer and stormwater backups on public and private properties. Prior to beginning design, building and system investigation for the entire project area was undertaken by the City’s consultants. Those investigations are necessary to understand how and where discharges from the sanitary sewer, sump pump, yard drain, driveway drain, stairwell drain and roof drains leave private property. In addition to the sewer separation work, the infrastructure design for each project area will include upgrades of water, cable, gas and electric.

The City will work with the community in developing an approach to surface improvements that address pedestrian, vehicular, landscaping, and environmental concerns for each of the project areas. Community meetings will be held to discuss neighborhood concerns and potential design solutions.

 

 

 

Cambridge Department of Public Works
147 Hampshire Street

cwoodbury@cambridgema.gov

Office hours are Mondays, 8:30 AM to 8 PM
Tuesday through Thursday, 8:30 AM to 5 PM
Fridays, 8:30 AM to 12 noon

 

For information related to the project design and construction please contact KyAnn Anderson, the DPW's Community Coordinator at (617) 498-4708/ Kanderson@kleinfelder.com or Catherine Daly Woodbury the DPW's Project Manager at 617.349.4818/ cwoodbury@cambridgema.gov.

 

 

How can we help you? I'd like...

Mobile Cambridge

Keeping you connected wherever you are. Learn more about Mobile Cambridge

FAQ's

Have a question?
Find the answer in our extensive
Frequently Asked Questions

Dept of Public Works

147 Hampshire St
Cambridge MA 02139

Phone:617.349.4800
TDD:617.499.9924

Hours of Service

Monday: 8:30am-8:00pm
Tuesday-Thursday: 8:30am-5:00pm
Friday: 8:30am-12 noon
24 Hour emergency 617.349.4860

RECYCLING CENTER HOURS

Tuesday & Thursday: 4:00pm-7:30pm
Saturday: 9:00am-4:00pm

Owen O'Riordan
Commissioner