U.S. flag

An official website of the United States government

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Harvard Square Kiosk and Plaza

In 2017, the City established a Harvard Square Kiosk and Plaza Working Group, composed of residents, business and property owners, representatives from local institutions, and urban design experts, to create a vision for the future use, operation, and governance of the Harvard Square Kiosk and Plaza.

The Working Group envisions the Harvard Square Kiosk and Plaza to be flexible, dynamic, and welcoming community assets that enhance the everyday life of Harvard Square, act as platforms for community gatherings, including civic, artistic, and social activities, and attract and serve a broad range of people, including residents, students, visitors, etc.

The interior of the Kiosk would function as a flexible space accommodating permanent and temporary community uses. Permanent uses would feature a Visitor Information Center with displays focused on Cambridge history and happenings and the provision of news, brochures, and other materials. Temporary uses would occupy a portion of the interior space intermittently during the span of a typical week, including informal public seating for gatherings. The Plaza would also accommodate a range of temporary programming serving the community. During periods of both temporary and regular use, the interior space would, in addition to acting as a space for relaxing, sitting, reading, meeting, etc., address in part key themes identified by Kiosk Working Group members and other participants in the public process, namely: local history, news, information about local events and services, and visitor information functions.

This project will be constructed in two phase: The Historic Out of Town News Kiosk Reconstruction and the Plaza Reconstruction. 

For more details about the community process of this project, including the Working Group Final Report, please visit: www.cambridgema.gov/harvardsquarekiosk

 

October 2023

Plantings, punch list items.


June 2023

Interior work continues. 


May 2023

Copper installation, and limestone cleaning. 


April 2023

Interior Work continues. 


November 2022

Masonry work, utility work, and framing. 


October 2022

Begin copper installation and interior plumbing and painting work. 


September 2022

Beginning the next phase of roof work and continuing masonry work on the headhouse.


August 2022

Continuing electrical work and waterproofing for the foundation. 


July 2022

Crews are excavating for waterproofing work and continuing electrical work. 


June 2022

Crews are prepping to begin removing the existing roof and installing new roof.  


May 2022

The City's contractor, Wes Construction, will be remobilizing the week of May 3. Crews will be performing masonry work, painting, and placement of structural steel.  


March 2022

Wes Construction anticipates remobilizing on site in April and completing the Kiosk project in November 2022. 

The plaza project bid is opening on 3/10/2022 at 2PM at City Hall, Purchasing Department. It is expected that a contractor will be on board in Spring 2022 and work beginning a few weeks later. 

The Community Development Department is working of an RFP for an operator for the Kiosk and expecting to have one onboard by early summer 2022. If you have questions about Kiosk operations, you can contact Melissa Peters, mpeters@cambridgema.gov.


June 2021

Over the next several weeks, the City's contractor, WES construction, will be performing demolition activities at the site. 


The City's contractor, WES Construction, will be mobilizing in the area of the Kiosk beginning Wednesday, May 19th. 


May 2021

The latest newsletter is now available


April 2021

The Out of Town News Kiosk Renovation contract has been awarded to WES Construction Corp. A detailed construction schedule will be available soon. 

Once the contractor has provided a schedule, a detailed timeline will be made available. 

For information about the community process for this project, including the complete Working Group Final Report, please visit www.cambridgema.gov/harvardsquarekiosk

Kristen Kelleher

Community Relations Manager

617-349-4825

kkelleher@cambridgema.gov

 

Melissa Miguel

Supervising Engineer

617-349-9351

mmiguel@cambridgema.gov

Sign Up Now

Page was posted on 4/13/2021 10:14 AM
Page was last modified on 4/8/2024 7:24 PM
Contact Us

How can we help?

Please provide as much detail below as possible so City staff can respond to your inquiry:

As a governmental entity, the Massachusetts Public Records Law applies to records made or received by the City. Any information received through use of this site is subject to the same provisions as information provided on paper.

Read our complete privacy statement


Service Requests

Enter a service request via SeeClickFix for things like missed trash pickups, potholes, etc.