Raymond Park, located at 106 Raymond Street in Neighborhood Nine, is scheduled for renovations beginning in November 2025. Planned improvements include:
- Improved circulation and more accessible pathways
- New playground equipment
- An expanded basketball court
- Drainage improvements and rain gardens
- Additional seating and gathering areas
- New trees and plantings
Learn more about the community and design process here.
May 2026:
Week of May 4: Drainage work, installation of catch basins, installation of loam, electrical work
Week of May 11: Electrical work, installation of lawn soil
April 2026:
Week of 4/13: The contractor will remobilize and prep the site to resume construction activities
Week of 4/20 (No work on Monday, Patriots Day): Crew on site working on field drainage
Week of 4/27: Drainage work continues
January 2026:
Construction work at Raymond Park is currently on hold due to cold weather conditions. Work will resume when warmer weather allows.
December 2025:
Week of 12/1: Install drainage structures near playground and continue installing base materials
Week of 12/8: Finish sub grading of field/build up sub grade in playground area, drainage work
Week of 12/15: Drainage work, removal of granite block walls
Week of 12/22: Begin placement of granite blocks
Week of 12/29: Start excavation of electrical duct bank
November 2025:
Week of 11/24: Install base material for playground structures
Construction Notice: Construction Expected to Start Week of November 17
We're pleased to announce the project contract, which includes the entire renovation, was awarded to J.J. Phelan & Son Co.
We expect construction to start the week of November 17. We're working to maintain access to the community garden and keep a small section of the park open for as long as the construction allows.
Construction is expected to take 12 - 18 months to complete. We will communicate any changes to that schedule as the project moves forward.
Please stay tuned by signing up for future emails to receive more details on the construction schedule.
November 2025: Construction to begin
Construction is expected to take 12-18 months to complete.
For questions relating to Raymond Park Construction, contact:
Kristen Kelleher
Community Relations Manager
City of Cambridge - Department of Public Works
617-349-4825
For questions relating to Raymond Park design, contact:
Cortney Kirk
ckirk@cambridgema.gov