This project has been completed. No further updates to this project page will be made.
June 19, 2017
Crews are working on final punch list items and clean up.
_______________________________________________________________________________________________________________________________________________________
June 12, 2017
Crews will pave Hurlbut St on Monday, June 12.
_________________________________________________________________________________________________________________________________________________________
June 5, 2017
Crews are expected to pave Hurlbut St on Monday, June 12, weather permitting.
________________________________________________________________________________________________________________________________________________________
May 30, 2017
Crews are expected to finish sidewalk reconstruction later this week, weather permitting.
On Monday, June 5, crews will mill the roadway on Hurlbut St to prepare for paving.
_________________________________________________________________________________________________________________________________________________________
May 15, 2017
Crews will continue with the sidewalk reconstruction this week. We expect the sidewalks to be complete by the end of May.
________________________________________________________________________________________________________________________________________________________
May 8, 2017
Crews will continue sidewalk reconstruction this week.
__________________________________________________________________________________________________________________________________________________________
May 1, 2017
Crews will continue on sidewalk reconstruction this week. This work will be ongoing for the next few weeks.
__________________________________________________________________________________________________________________________________________________________
April 10, 2017
Crews will mobilize this week to start replacing select lead water services. Once this is complete, crews will begin sidewalk reconstruction.
________________________________________________________________________________________________________________________________________________________
April 3, 2017
Due to unfavorable weather conditions, crews will now resume construction activities on Hurlbut St during the week of April 10. Crews will begin with lead water service replacement.
________________________________________________________________________________________________________________________________________________________
March 29, 2017
Crews will return to Hurlbut St on Monday, April 3 to resume construction activities. Work will be ongoing for the next month, starting with lead water service replacement, sidewalk reconstruction, then roadway paving.
________________________________________________________________________________________________________________________________________________________
December 22, 2016
Crews will mobilize on Hurlbut St during the week of December 27.
__________________________________________________________________________________________________________________________________________________________
November 2016
Crews are expected to perform drainage work on Hurlbut St in mid-December.
____________________________________________________________________________________________________________________________________________________________
September 2016
The city is in the process of awarding the contract. We expect to have a schedule by the end of September. Please check back for updates.
_____________________________________________________________________________________________________________________________________________________________________
June 2016
The city will put this contract out to bid this summer. We expect construction to start in the fall. Please check back for updates.
_____________________________________________________________________________________________________________________________________________________________________
October 2015
The Department of Public Works and the City’s Community Development Department hosted the second community meeting to discuss the Hurlbut Street Reconstruction Project on Wednesday, October 14 at 6:30pm, at the Graham and Parks School auditorium located at 44 Linnaean Street.
During this meeting a conceptual plan was presented that includes new sidewalks and creates an accessible sidewalk route that meets access codes and addresses the needs of all users.
This project is a part of the City’s five year plan for street and sidewalk reconstruction, and the Hurlbut Street project is scheduled to begin in Spring 2016.
_____________________________________________________________________________________________________________________________________________________________________
Summer 2015
There is no scheduled work or community meetings scheduled for the summer months. Over the summer months, city staff will be working with select residents regarding accessibility issues. Another community, where the draft design will be presented, will take place in Fall 2015.