Eliot Street Reconstruction Project

Following gas main replacement by Eversource, Eliot St., between John F. Kennedy St. and Bennett St., is scheduled for sidewalk and street reconstruction in 2019. This work will entail adding drainage structures to the street, replacing the water main, reconstructing the sidewalks and re-paving the street. 

August 2019

Crews have encountered a few unforeseen conflicts with utilities in the area which has resulted in a delay in setting curbs and reconstructing sidewalks. The appropriate utility companies have been on-site trying to resolve these issues and we anticipate work to resume the week of 8/12. 


A diagram of the pavement markings has been uploaded to the "Document" tab of the project page. 


June 2019

6/2/2019-6/6/2019: No work scheduled

6/9/2019-6/20/2019: Crews will continue to replace water main and services. In addition, they will continue providing conduit for the new street light poles.

6/23/2019-7/19/2019: Pending completion of the water and electrical work, crews will begin replacing and resetting curbs, grading sidewalks and installing pavers. 


May 2019

5/13-5/24: Crews will be working to replace the water main and lay conduit as weather permits. There will be no work the week of 5/27 to accommodate Harvard Commencement. 


April, 2019:

Once Eversource is done with their work replacing the gas main and services, crews from the City's contractor, Newport Construction, will be mobilizing in advance of drainage work. This will entail installing tree protection and doing some subsurface investigations. 

April, 2019: Eversource Gas completes gas main and service replacements. Tree protection installed. Subsurface condition inspections.

May 2019: drainage installations. Water main replacement.

June 2019: water main replacement.

July/August 2019: curb and sidewalk replacement

July 2019: traffic signal and electrical work

August 2019: final paving of roadway, pavement markings.

Kate Riley - Community Relations Manager

kriley@cambridgema.gov

617-349-4870


Melissa Miguel - Supervising Engineer

mmiguel@cambridgema.gov

617-349-9351


Sign Up Now

Page was posted on 4/4/2019 10:00 AM
Page was last modified on 8/7/2019 3:14 PM
Provide Feedback

Got feedback?

Please provide your feedback below: