The Foundry

Project Image

The Foundry Building at 101 Rogers Street was acquired by the city as the result of a real estate development proposal from Alexandria Real Estate involving a number of parcels in an adjacent sector of the Kendall Square area. The City's acquisition of 101 Rogers Street included the stipulation that a minimum of 10,000 square feet would be dedicated to community use. The property is currently vacant. In May 2015 the City Council approved a partnership with the Cambridge Redevelopment Authority (CRA) including the city's disposition and demonstration plans for the building.

The Foundry is an adaptive reuse project to build a self-sustaining center for creativity and collaboration for the Cambridge community. At the intersection of the Kendall Square Innovation District and the East Cambridge neighborhood, the Foundry building will provide space and programs for the visual and performing arts, entrepreneurship, technology, and workforce education within its historic, industrial setting. The Foundry will also help facilitate access for residents, especially underrepresented communities and adjacent neighborhoods, to the dynamic working and learning environment of Kendall Square.

April 2021

  • Complete Masonry reconstruction
  • Complete structural steel erection for building addition
  • Start installation of new roof assembly
  • Install 2nd & 3rd Floor concrete slabs on deck at building addition
  • Install underslab Plumbing and Electrical

 

Interior Construction of The Foundry

Exterior Construction at The Foundry


February 2021

  • Install site drainage and electrical utilities
  • Continue Masonry demolition and reconstruction
  • Structural steel erection for building addition
  • Install 3rd Floor concrete slab on deck at existing building
  • Install underslab Plumbing and Electrical at existing building

Construction Progress Pictures

Interior Construction Pictures of The FoundryInterior Construction Pictures of The Foundry

 


September 2020

  • Complete Interior Excavation

  • Install Support of Excavation

  • Install concrete foundation in existing building and new addition.


July 2020

Week of 7/6: Debris removal associate with the stucco additional on the west side

Week of 7/13: Removal of the roof mechanical components, equipment and skylights

Week of 7/20: Removal of existing concrete basement slab


June 2020

The schedule for this project has been updated due to delays caused by the COVID-19 pandemic. Please see the "Schedule" tab for details. 


February 2020

Selective demolition work will continue through the spring 2020. The City's contractor W.T. Rich, will be removing interior walls, interior floor slabs, windows and mono-truss timers. In addition, they are removing the stucco elevation, the façade facing Verizon property, the roof mechanical equipment, and skylights. They will also be installing temporary roof protection. 


Interior Demolition Pictures:

Interior pic of the demolition of the building

Interior pic of demolition of the building

The following schedule has been updated as of April 2021

Spring 2021:  Complete new roof assembly.  Install 1st Floor concrete slab on grade. Install exterior envelope.  Begin interior work.

Summer & Fall 2021:  Site improvements.  Interior work will continue.

Winter 2021 & Spring 2022:  Interior work will continue.

Summer 2022:  Building complete.


The following schedule has been updated as of February 2021

Winter 2021:  Complete installation of structural steel.  Install interior concrete floors.

Spring 2021:  Install exterior envelope.  Begin interior work.

Summer, Fall, Winter 2021 & Spring 2022:  Interior work will continue.

Summer 2022:  Building complete.


The following schedule has been updated as of September 2020

Fall 2020: Installation of concrete foundation, roofing and Masonry restoration.  Begin installation of structural steel.

Winter 2020-21:  Complete installation of structural steel.  Install interior concrete floors.

Spring 2021:  Install exterior envelope.  Begin interior work.

Summer, Fall, Winter 2021:  Interior work will continue.

Spring 2022:  Building complete.


The following schedule has been updated as of June 2020

Summer 2020:  Equipment, interior walls, interior floor slabs and windows have been removed. Selective demolition will continue with the exterior removal of the stucco elevation, the façade facing Verizon property, the roof mechanical equipment, the skylights and the roof.  Installation of temporary roof protection and concrete foundation.

Fall 2020: Installation of structural steel, new roof and Masonry restoration.

Late Fall 2020: the renovated building and the new building addition will be enclosed, and interior work will begin.

Winter, Spring, Summer 2021: Interior work will continue

Late Fall 2021: building complete


December 2019 through May 2020: Selective Demolition. Includes removal of equipment, interior walls, interior floor slabs, windows, mono-truss timbers.  Exterior removal of stucco elevation, façade facing Verizon property, roof mechanical equipment, skylights.  Installation of temporary roof protection.

Spring/Summer 2020: the schedule needs to be finalized but will include: Installing site utilities, Masonry restoration, installing new roof, installing foundations and structural steel.

Late Fall 2020: the renovated building and the new building addition will be enclosed and interior work will commence.

Summer 2021: building complete.

For background information, including information about the community process for this project, please visit: https://www.cambridgeredevelopment.org/foundry

 

Brendon Roy- Construction Program Manager

617-349-4300

broy@cambridgema.gov

 

Kate Riley- Community Relations Manager

617-349-4870

kriley@cambridgema.gov

Sign Up Now

Page was posted on 2/25/2020 10:12 AM
Page was last modified on 4/1/2021 10:35 AM
Contact Us

How can we help?

Please provide as much detail below as possible so City staff can respond to your inquiry:

As a governmental entity, the Massachusetts Public Records Law applies to records made or received by the City. Any information received through use of this site is subject to the same provisions as information provided on paper.

Read our complete privacy statement


Service Requests

Enter a service request via Commonwealth Connect for things like missed trash pickups, potholes, etc.