February 2021
- Install site drainage and electrical utilities
- Continue Masonry demolition and reconstruction
- Structural steel erection for building addition
- Install 3rd Floor concrete slab on deck at existing building
- Install underslab Plumbing and Electrical at existing building
Construction Progress Pictures


September 2020
-
Complete Interior Excavation
-
Install Support of Excavation
-
Install concrete foundation in existing building and new addition.
July 2020
Week of 7/6: Debris removal associate with the stucco additional on the west side
Week of 7/13: Removal of the roof mechanical components, equipment and skylights
Week of 7/20: Removal of existing concrete basement slab
June 2020
The schedule for this project has been updated due to delays caused by the COVID-19 pandemic. Please see the "Schedule" tab for details.
February 2020
Selective demolition work will continue through the spring 2020. The City's contractor W.T. Rich, will be removing interior walls, interior floor slabs, windows and mono-truss timers. In addition, they are removing the stucco elevation, the façade facing Verizon property, the roof mechanical equipment, and skylights. They will also be installing temporary roof protection.
Interior Demolition Pictures:


The following schedule has been updated as of February 2021
Winter 2021: Complete installation of structural steel. Install interior concrete floors.
Spring 2021: Install exterior envelope. Begin interior work.
Summer, Fall, Winter 2021 & Spring 2022: Interior work will continue.
Summer 2022: Building complete.
The following schedule has been updated as of September 2020
Fall 2020: Installation of concrete foundation, roofing and Masonry restoration. Begin installation of structural steel.
Winter 2020-21: Complete installation of structural steel. Install interior concrete floors.
Spring 2021: Install exterior envelope. Begin interior work.
Summer, Fall, Winter 2021: Interior work will continue.
Spring 2022: Building complete.
The following schedule has been updated as of June 2020
Summer 2020: Equipment, interior walls, interior floor slabs and windows have been removed. Selective demolition will continue with the exterior removal of the stucco elevation, the façade facing Verizon property, the roof mechanical equipment, the skylights and the roof. Installation of temporary roof protection and concrete foundation.
Fall 2020: Installation of structural steel, new roof and Masonry restoration.
Late Fall 2020: the renovated building and the new building addition will be enclosed, and interior work will begin.
Winter, Spring, Summer 2021: Interior work will continue
Late Fall 2021: building complete
December 2019 through May 2020: Selective Demolition. Includes removal of equipment, interior walls, interior floor slabs, windows, mono-truss timbers. Exterior removal of stucco elevation, façade facing Verizon property, roof mechanical equipment, skylights. Installation of temporary roof protection.
Spring/Summer 2020: the schedule needs to be finalized but will include: Installing site utilities, Masonry restoration, installing new roof, installing foundations and structural steel.
Late Fall 2020: the renovated building and the new building addition will be enclosed and interior work will commence.
Summer 2021: building complete.